Fifteen days is the honest number for a new position count on an existing 2.54 mm header family, and about 25–30 days for a genuinely new mold. The mold being on site saves freight, not queue time: a modified mold still has to be pulled from production, cut, polished, trialled, sampled and plated.

Buyers usually hear "we make our own molds" and expect a week. The confusion is between machining time and the time the part spends waiting for the next step.

Where the days actually go

Step Days What can go wrong
Mold pulled from production, insert changed 2–3 Mold is mid-run for another customer
Trial shot and dimensional check 1–2 Flash or short shot on the new cavity
First article inspection, report 1–2 Coplanarity out of tolerance on long bodies
Stamping and pin insertion setup 1–2 Pin reel for that position count not in stock
Plating run 2–3 Barrel plating queue; selective plating needs masking
Final inspection and packing 1 AQL sample fails, run repeats

Six steps, and each one has a queue in front of it. The machining itself is hours. The elapsed time is the sum of waits.

Why a new mold is a different project

A new position count inside an existing family reuses the mold base and changes an insert. A new pitch, a new body height or a new contact geometry needs a new mold: design, steel, EDM, heat treatment, trial, correction, trial again. That is 25–30 days and a tooling charge, and the charge is usually amortised over the first order rather than paid upfront.

Position counts outside the standard range are the usual trigger. 2×5 to 2×40 covers most requests; 2×2 or 2×50 does not.

What you can do to shorten it

  • Order prototype quantity from the standard mold and cut it down. A 2×40 cut to 2×13 is a same-week sample with a sawn edge.
  • Accept the standard plating on the first article and change thickness later; plating setup is one of the longer queues.
  • Send the drawing with tolerances on the features that matter. Ambiguity turns into a second first-article loop.
  • Book the mold slot before you finish the drawing if the schedule is tight. The queue is the constraint, not the design.

What we do not do

We do not quote a 7-day tooling lead time to win an order and then explain the delay later. If the mold is busy, the date moves and you hear it on the day we know, not the day it ships.

Can I get samples before the tool is finished?

Usually yes, from the nearest standard position count, cut to size. It will not have the exact end wall, so treat it as a fit check, not a qualification sample.

Is the tooling charge refundable?

On repeat orders above an agreed volume, we credit it back. Below that, the charge covers the steel and the setup, and the mold stays ours unless you buy it out.

Does a new position count change the price per piece?

Only through volume. The piece price is driven by pin count and plating, and a 2×13 costs less than a 2×40 because there is less metal in it.

If you have a position count outside the standard range, send it with the annual volume and we will tell you whether it is an insert change or a new mold before you commit to a schedule. See our tooling and molding capability.